Agenda Item #3 FY 2023-2026 Transportation Improvement Program (TIP) Amendments
The City of Knoxville requested the following amendments:
Existing Pleasant Ridge Road project - Amend project to revise the project schedule and increase the construction phase cost and total project cost. Construction is programmed in FY 2025 at a total cost of $14,784,512 ($9,048,890 federal L-STBG/$2,262,222 local/$3,474,400 local non-participating). This amendment adds $9,287,795 (+$4,650,716 federal/+$1,162,679 local/+$3,474,400 local non-participating) to the project and the TIP. The total project cost is increased to $17,459,821.
Existing Liberty Street Multimodal project - Amend project to revise the project schedule and increase the construction phase cost and total project cost. Additional PE-D programming is removed. Construction is programmed in FY 2025 at a total cost of $1,525,419 ($561,920 federal L-STBG/$658,415 federal L-STBG-TA/$305,084 local. This amendment adds $817,555 (+$658,415 federal L-STBG-TA/-$4,371 federal L-STBG/+$163,511 local) to the project and the TIP. The total project cost is increased to $2,262,455.
Attachment #3A: 23-2014-037 Draft Amendment
Attachment #3B: 23-2014-080 Draft Amendment
Attachment #3C: Draft TIP Amendment Resolution
Attachment #3D: Draft Metropolitan Planning Process Self-Certification